Anchor ads are not supported on this page.

4S Ranch Allied Gardens Alpine Baja Balboa Park Bankers Hill Barrio Logan Bay Ho Bay Park Black Mountain Ranch Blossom Valley Bonita Bonsall Borrego Springs Boulevard Campo Cardiff-by-the-Sea Carlsbad Carmel Mountain Carmel Valley Chollas View Chula Vista City College City Heights Clairemont College Area Coronado CSU San Marcos Cuyamaca College Del Cerro Del Mar Descanso Downtown San Diego Eastlake East Village El Cajon Emerald Hills Encanto Encinitas Escondido Fallbrook Fletcher Hills Golden Hill Grant Hill Grantville Grossmont College Guatay Harbor Island Hillcrest Imperial Beach Imperial Valley Jacumba Jamacha-Lomita Jamul Julian Kearny Mesa Kensington La Jolla Lakeside La Mesa Lemon Grove Leucadia Liberty Station Lincoln Acres Lincoln Park Linda Vista Little Italy Logan Heights Mesa College Midway District MiraCosta College Miramar Miramar College Mira Mesa Mission Beach Mission Hills Mission Valley Mountain View Mount Hope Mount Laguna National City Nestor Normal Heights North Park Oak Park Ocean Beach Oceanside Old Town Otay Mesa Pacific Beach Pala Palomar College Palomar Mountain Paradise Hills Pauma Valley Pine Valley Point Loma Point Loma Nazarene Potrero Poway Rainbow Ramona Rancho Bernardo Rancho Penasquitos Rancho San Diego Rancho Santa Fe Rolando San Carlos San Marcos San Onofre Santa Ysabel Santee San Ysidro Scripps Ranch SDSU Serra Mesa Shelltown Shelter Island Sherman Heights Skyline Solana Beach Sorrento Valley Southcrest South Park Southwestern College Spring Valley Stockton Talmadge Temecula Tierrasanta Tijuana UCSD University City University Heights USD Valencia Park Valley Center Vista Warner Springs

Affordable Housing Project Delayed by California Supreme Court

After the Cortez “hole” was finally filled and chainlink-fenced in August 2010 (click here for background), the plan was to transform the empty lot owned by the San Diego Redevelopment Agency into a paved and lighted parking lot.

The site is midblock between Ash and Beech streets, in between Fourth and Fifth avenues. The Centre City Development Corporation solicited bids for the $145,000 project last March.

Sponsored
Sponsored

I went by last week to take a look. Unlike some abandoned construction sites, it's clean and secured. I contacted Jeff Graham, vice president for redevelopment at Centre City Development Corporation, to find out what brought the project to a halt.

Graham said, “The California Supreme Court agreed to accept the litigation filed by the League of California Cities and the California Redevelopment Association challenging the constitutionality” of California Assembly bills ABx1 26 and ABx1 27.

“Therefore, CCDC and the [Redevelopment] Agency are unable to proceed with executing the contract with the low bidder to construct the parking-lot improvements or any other project at this time.”

Graham said “dozens of projects” in 14 redevelopment-project areas had been delayed.

“To say that the legislation and the court order are frustrating and detrimental to the local economy and downtown would be an understatement,” he said.

The parking lot project includes revenue sharing between the parking operator and the Redevelopment Agency. The parking lot would remain until a planned low-income apartment complex (“Atmosphere”) begins construction.

The affordable-housing developer, Wakeland Housing & Development Corporation, has, according to Graham, “taken the proposed project through the design-review process but staff is unable to [proceed] under the current Supreme Court stay order."

Here's something you might be interested in.
Submit a free classified
or view all
Previous article

Gonzo Report: Kavana takes the stage at Navajo Live

Sparse crowd doesn’t lessen metal magic

After the Cortez “hole” was finally filled and chainlink-fenced in August 2010 (click here for background), the plan was to transform the empty lot owned by the San Diego Redevelopment Agency into a paved and lighted parking lot.

The site is midblock between Ash and Beech streets, in between Fourth and Fifth avenues. The Centre City Development Corporation solicited bids for the $145,000 project last March.

Sponsored
Sponsored

I went by last week to take a look. Unlike some abandoned construction sites, it's clean and secured. I contacted Jeff Graham, vice president for redevelopment at Centre City Development Corporation, to find out what brought the project to a halt.

Graham said, “The California Supreme Court agreed to accept the litigation filed by the League of California Cities and the California Redevelopment Association challenging the constitutionality” of California Assembly bills ABx1 26 and ABx1 27.

“Therefore, CCDC and the [Redevelopment] Agency are unable to proceed with executing the contract with the low bidder to construct the parking-lot improvements or any other project at this time.”

Graham said “dozens of projects” in 14 redevelopment-project areas had been delayed.

“To say that the legislation and the court order are frustrating and detrimental to the local economy and downtown would be an understatement,” he said.

The parking lot project includes revenue sharing between the parking operator and the Redevelopment Agency. The parking lot would remain until a planned low-income apartment complex (“Atmosphere”) begins construction.

The affordable-housing developer, Wakeland Housing & Development Corporation, has, according to Graham, “taken the proposed project through the design-review process but staff is unable to [proceed] under the current Supreme Court stay order."

Comments
Sponsored
Here's something you might be interested in.
Submit a free classified
or view all
Previous article

Two poems by Willa Cather

Famed author’s “Prairie Spring” and “Evening Song”
Next Article

Toni Atkins sucks in money from ultra rich

Union-Tribune parent Alden attacks Google for using its content and keeping users on Google
Comments
Ask a Hipster — Advice you didn't know you needed Big Screen — Movie commentary Blurt — Music's inside track Booze News — San Diego spirits Classical Music — Immortal beauty Classifieds — Free and easy Cover Stories — Front-page features Drinks All Around — Bartenders' drink recipes Excerpts — Literary and spiritual excerpts Feast! — Food & drink reviews Feature Stories — Local news & stories Fishing Report — What’s getting hooked from ship and shore From the Archives — Spotlight on the past Golden Dreams — Talk of the town The Gonzo Report — Making the musical scene, or at least reporting from it Letters — Our inbox Movies@Home — Local movie buffs share favorites Movie Reviews — Our critics' picks and pans Musician Interviews — Up close with local artists Neighborhood News from Stringers — Hyperlocal news News Ticker — News & politics Obermeyer — San Diego politics illustrated Outdoors — Weekly changes in flora and fauna Overheard in San Diego — Eavesdropping illustrated Poetry — The old and the new Reader Travel — Travel section built by travelers Reading — The hunt for intellectuals Roam-O-Rama — SoCal's best hiking/biking trails San Diego Beer — Inside San Diego suds SD on the QT — Almost factual news Sheep and Goats — Places of worship Special Issues — The best of Street Style — San Diego streets have style Surf Diego — Real stories from those braving the waves Theater — On stage in San Diego this week Tin Fork — Silver spoon alternative Under the Radar — Matt Potter's undercover work Unforgettable — Long-ago San Diego Unreal Estate — San Diego's priciest pads Your Week — Daily event picks
4S Ranch Allied Gardens Alpine Baja Balboa Park Bankers Hill Barrio Logan Bay Ho Bay Park Black Mountain Ranch Blossom Valley Bonita Bonsall Borrego Springs Boulevard Campo Cardiff-by-the-Sea Carlsbad Carmel Mountain Carmel Valley Chollas View Chula Vista City College City Heights Clairemont College Area Coronado CSU San Marcos Cuyamaca College Del Cerro Del Mar Descanso Downtown San Diego Eastlake East Village El Cajon Emerald Hills Encanto Encinitas Escondido Fallbrook Fletcher Hills Golden Hill Grant Hill Grantville Grossmont College Guatay Harbor Island Hillcrest Imperial Beach Imperial Valley Jacumba Jamacha-Lomita Jamul Julian Kearny Mesa Kensington La Jolla Lakeside La Mesa Lemon Grove Leucadia Liberty Station Lincoln Acres Lincoln Park Linda Vista Little Italy Logan Heights Mesa College Midway District MiraCosta College Miramar Miramar College Mira Mesa Mission Beach Mission Hills Mission Valley Mountain View Mount Hope Mount Laguna National City Nestor Normal Heights North Park Oak Park Ocean Beach Oceanside Old Town Otay Mesa Pacific Beach Pala Palomar College Palomar Mountain Paradise Hills Pauma Valley Pine Valley Point Loma Point Loma Nazarene Potrero Poway Rainbow Ramona Rancho Bernardo Rancho Penasquitos Rancho San Diego Rancho Santa Fe Rolando San Carlos San Marcos San Onofre Santa Ysabel Santee San Ysidro Scripps Ranch SDSU Serra Mesa Shelltown Shelter Island Sherman Heights Skyline Solana Beach Sorrento Valley Southcrest South Park Southwestern College Spring Valley Stockton Talmadge Temecula Tierrasanta Tijuana UCSD University City University Heights USD Valencia Park Valley Center Vista Warner Springs
Close

Anchor ads are not supported on this page.