• Story alerts
  • Letter to Editor
  • Pin it

On May 27, Shifflet advised Hanson to pursue these deeper inquiries through a Public Records Act request. She even supplied him with the number of the bid that Heffler won.

But the next day, Shifflet wrote Hanson that she had “to make a correction to the method of how we hired Heffler.… In April 2006 the Park and Recreation Department requested the Contract Services Department to provide a sole source contract for the Beyer Boulevard project.… Several projects were submitted…for the use of the [$1 million grant] money but were turned down by the State. In 2005 the State agreed to the Beyer Boulevard Ranger station and trail, but the money had to be paid out by June 2007. City [and other] permits were obtained in September 2006. One of the permit conditions was that construction could not occur during the bird-breeding season. This only allowed construction to occur from September 16 to March 15. [Thus] the construction schedule…did not allow for a three month public bid process and…a sole source contract was requested and approved.”

Shifflet sent one final email to Hanson. It included an amendment to Heffler’s cost summary sheet for the Beyer staging area. The amended summary detailed how the project reached its $500,000 overrun. Perhaps many costs had been anticipated from the project’s beginning, for the summary showed that $382,639 was administrative expenses, including $215,910 to the City. But $135,053 was new construction costs. Of these, $104,536 came in two project “change orders.”

The Heffler Company, Inc., of National City, founded by contractor Patrick Heffler, has completed numerous projects for the San Diego Park and Recreation Department. The company has often gone back for “change orders,” according to the minutes of the San Diego City Council. At city council meetings, one often sees change orders approved for construction projects. After searching meeting minutes, I am unable to find approval of the change orders Heffler received for the Beyer staging area.

Costs are one thing, quality of what you pay for quite another. George Hanson tells me of a different San Diego County open-space park facility he recently visited. The Goodan Ranch/Sycamore Canyon Visitors Center, a 3200-square-foot building near Poway, opened in November to replace a center that was burned to the ground in the 2003 Cedar Fire. “The new building has a mini theater and a number of green aspects, such as solar paneling on the roof. It’s very impressive.”

(Costs increased in the Goodan Ranch project as well. When I called Mina Nguyen, spokeswoman for the San Diego County Parks and Recreation Department, she was tight-lipped about the project’s final costs. But North County Times’ reports had put the bill originally at $1.4 million, then $1.5 and $1.7 million. The most recent figure I found came from the San Diego Union-Tribune, a little over $2 million.)

Hanson says that during meetings of the Otay Valley Regional Park’s Citizen Advisory Committee, his inquiries into finances were met with less than enthusiasm. At mention of possible irregularities, he said, one member’s “whole face looked like it dropped.” In the give-and-take of the committee’s June meeting, Hanson tells me, vice chairman Kevin O’Neil admonished him that it is not the charge of members to raise such questions. It gave Hanson a new metaphor for understanding what a citizen advisory committee is. “Remember in the old days,” he asks, “those play steering wheels for kids in cars?”

  • Story alerts
  • Letter to Editor
  • Pin it

Comments

rexl Aug. 21, 2008 @ 9:46 a.m.

we had a general contracting firm that did hard bid, fully bonded public work like that in the article for the same agencies and many more around the county. A job is bid from a set of 'plans and specs', these plans and specifications are not drawn or put together by the contractor. The contractor is told to bid only what is in the plans and specs, nothing more and nothing less. If the contractor should miss something or underestimate the cost of doing a task he must nonetheless complete the task and work per the plans and specs. The contractor wants to build the project, be done and get paid. However if there is a problem with the plans and specs, or if the contracting agency (the owner) wants something changed once the contract is signed then the extra work or if the change in scope requires extra material and labor then someone has to pay or the contractor does not have to do the work. period. so the contract states (which you would discover if you looked at one of those voluminous objects) that a change order must be signed and approved, usually prior to doing the extra work, although every contractor in the business has done change order work for which they were never compensated. so it is not the "company that has gone back for change orders" as much as it is the lack of planning or completeness of the plans and specs that has REQUIRED change orders by issued.
These "problems" come to light when the contractor actually begins the work, which is when the rubber meets the road. surely

0

rexl Aug. 21, 2008 @ 9:55 a.m.

surely, a teacher of remedial english understands rubber meeting the road. and the part about your friend could build for $85-$100 per square foot, when applied to public buildings, particularly small ones is ignorance speaking. I am not familiar with Heffler, but they have been around for some time, and I have no opinion on them. There are some bad contractors out there but when a project costs more than all the planners, thinkers and administrators planned and thought it would. The location of the problem is pretty obvious and that doesn't require a change order, because it is the same old ----.

0

Sign in to comment

Join our
newsletter list

Enter to win $25 at Broken Yolk Cafe

Each newsletter subscription
means another chance to win!

Close