But it's okay when the city's permit expires

Mission Beach lifeguard station project still hung up in court

South Mission Beach lifeguard station

Former development services directors for the City of San Diego say it is standard operating procedure to allow building permits for city projects to lapse while funding is procured and outside permits are obtained.

In the case of the proposed Mission Beach Lifeguard Tower, the process took nine years: from September 2006, when the city first obtained a permit, to May 2015, when crews appeared at the beach to get started on construction of a slightly modified project.

Last month, Superior Court judge Katherine Bacal ordered the city to halt construction on the 3990 square-foot lifeguard tower in South Mission Beach after a group of residents filed a lawsuit against the city claiming that the city's permits had expired.

Sponsored
Sponsored

Their argument hinges on language in the permit that requires that "[c]onstruction, grading or demolition must commence and be pursued in a diligent manner within thirty-six months after the effective date of final approval by the City, following all appeals. Failure to utilize the permit within thirty-six months will automatically void the permit unless an Extension of Time has been granted."

Residents also objected to what they say was a lack of notification from the city about the status of the project.

"We are fine with building something reasonable, a state-of-the-art station," Mission Beach resident and member of Citizens for Beach Rights Ken Giavara told the Reader in an October interview.

"Our ultimate goal is bring it back to the public. The reason permits have expiration dates is because neighborhoods change, zoning laws change, environmental laws change, and technology changes. A lot has changed since they got this permit...."

In court declarations, former building directors for the city said that it was common to postpone city projects for months and years longer than the permit allowed in order to allow time to acquire additional permits and to find funding.

"If a project was going though the [Capital Improvements Program] process, [the Development Services department] considered that utilization of the permit because the City cannot pursue other regulatory approvals without the proper funding in place and the complexity of going through the [process] is an obstacle that private developers do not encounter," said former director Kelly Broughton in a November 10 declaration.

Continued Broughton, "[Development Services] considered the fact that the city was actively going through the [Capital Improvements Program] process for its funding as evidence that it has not abandoned the project and was, in fact, utilizing its permit. At no time did [Development Services] consider the project abandoned nor did [Development Services] consider the Permit void. With respect to the Project at issue, the fact that the city was pursuing a Coastal Development Permit simultaneously while undergoing the [Capital Improvements Program] process was sufficient evidence of permit utilization and consistent with how [Development Services] interpreted the permit utilization statute."

To bolster their argument, the city also obtained testimony from former building director Marcela Escobar-Eck.

"When the city is an applicant for a development permit, it faces constraints that typical applicants are not subject to as it relates to funding. Private developers have numerous resources from which to obtain funding for their projects that do not require a months-long — or in many cases, years-long — process. Here, under the city's charter, the city cannot enter into contracts with consultants like architects or contractors for a project unless a funding source has first been identified. With respect to the project at issue, the fact that the city was pursuing a Coastal Development Permit simultaneously while undergoing the [process] would have been sufficient evidence of permit utilization and consistent with how [development services] interpreted the permit utilization statute."

The civil trial will begin on Wednesday, November 18, in Department 69 at 9 a.m. inside the downtown courthouse.