Normal Heights’ “sewer line project from hell” addressed

Police also attend peaceful but rowdy meeting

Workers at 33rd Street and Meade Avenue, January 7, 2013

On the evening of June 26, about three dozen people from the neighborhood around 33rd Street in Normal Heights finally learned the details of what one resident called "the sewer line project from hell.”

Five San Diego police officers also were there, working on overtime to monitor the peaceful but rowdy meeting.

Project 767, originally awarded in March 2012 at $2.9 million, was supposed to last about 28 weeks. Instead, the price went up to $3.8 million and the project stretched to a year, during which sections of the pipe were torn up again and again — or so it seemed to residents.

The streets were trenched deep, and heavy equipment, steel plates, and enormous pipes blocked driveways and provided continual noise and dust. The water main was broken and cut off at least five times, power lines were crushed (causing a ten-hour-long power outage), and streets (from I-805 to Felton Street and from El Cajon Boulevard to Meade Avenue) were closed again and again.

Sponsored
Sponsored

"What we really want is an apology, and what we're getting is a laundry list of what occurred," a 33rd Street resident named Ted said at the meeting. "We should have been told while we were living through it."

Dave Zoumaras from the city's Department of Public Works explained that when the contractor dug down the 18 to 20 feet to get to the sewer line, well below the water lines at three to five feet, they found unstable soil conditions, made worse by the “crush weight” of the six to ten feet of heavy, wet clay above it.

"We expect there to be problem areas, but we do not expect every foot of a project to be a challenge," Zoumaras said. "It was a struggle every foot of the way."

Unstable soil conditions hampered progress considerably, said a Department of Public Works employee.

The dry, loose soil beneath the clay shifted so much that Cass Construction had to fill trenches before they went home because they weren't stable enough to cover and leave overnight, Zoumaras said. And the water line they were supposed to leave in place and dig around was at least 60 years old and broke repeatedly. Replacing the water line had to be incorporated into the job.

"We did not make a dime on this — we lost a substantial amount of money on this project," said Kyle Nelson, president of Cass Construction. If he had the chance to bid the project again, he added, he would run away.

That unstable soil may be why residents' sidewalks, curbs, and porches are now collapsing, residents said.

"They were banging so hard that things fell off the walls," a resident said. "We literally felt 7.0 tremors for weeks and weeks of pounding, all day every day."

Residents were directed to submit claims to the city's Risk Management Office, but some said they'd already been rejected.

"You've just been given the finger," Steve Graham said.

Some residents said that “no parking” signs were added for the construction and that they are still garnering tickets, even though the construction ended in May. And there were a couple of days when cars were towed off 33rd Street with no warning to the owners.

The Public Works staff promised to work with Todd Gloria's office to support people in getting their tickets dismissed and towing charges refunded.

Nelson, from Cass Construction, and the Public Works Engineering Division staff said that they have spent a lot of time in meetings figuring out what went wrong — from unexpected soil conditions to leaving residents in the dark.

"The number-one lesson here is that we need to communicate better," said Tony Heinrichs, director of the Public Works Department. "We're going to do a better job of letting people know what's going on in a timely fashion."

Although a lot of factual information was provided, the forum didn't allow for much venting of anger and frustration, and there was much to go around.

"What we really want is an apology," said Carrie Spillane. "What we're getting is ‘okey-dokey,’ and you know what that really means."

(revised 8:45 a.m., 6/28)

Related Stories